HMDC submitted a project description for a proposed drill centres construction and operations program on the Grand Banks and within the Jeanne d’Arc Basin over the period 2009 through 2036. The project is listed on the Inclusion List Regulations under the CEA Act and requires a Screening level of assessment. The following is a list of documents available on the public registry for the project.

Scroll to view more

Date Record Author

15 Oct, 2019

Electronic transmission of Revised EA Update for 2019 to NGO Fisheries

C-NLOPB

15 Oct, 2019

Electronic transmission of Revised EA Update for 2019 to government departments and agencies

C-NLOPB

15 Oct, 2019

Electronic transmission of Revised EA Update for 2019 to Responsible Authorities

C-NLOPB

30 Sep, 2019

Revised 2019 Environmental Assessment Update

HMDC

26 Apr, 2019

Electronic transmission of EA Update for 2019 to NGO Fisheries

C-NLOPB

26 Apr, 2019

Electronic transmission of EA Update for 2019 to government departments and agencies

C-NLOPB

26 Apr, 2019

Electronic transmission of EA Update for 2019 to Responsible Authorities

C-NLOPB

15 Apr, 2019

Submission of 2019 Environmental Assessment Update

HMDC

10 Apr, 2019

2019 Environmental Assessment Update

HMDC

23 Feb, 2018

2018 Environmental Assessment Update

HMDC

23 Feb, 2018

Submission of 2018 Environmental Assessment Update

HMDC

30 Mar, 2017

Electronic transmission of EA Update for 2017 to NGO Fisheries

C-NLOPB

30 Mar, 2017

Electronic transmission of EA Update for 2017 to government departments and agencies

C-NLOPB

30 Mar, 2017

Electronic transmission of EA Update for 2017 to Responsible Authorities

C-NLOPB

28 Feb, 2017

2017 Environmental Assessment Update

HMDC

28 Feb, 2017

Submission of 2017 Environmental Assessment Update

HMDC

10 Mar, 2016

Electronic transmission of Revised EA Update for 2016 to NGO Fisheries

C-NLOPB

10 Mar, 2016

Electronic transmission of Revised EA Update for 2016 to government departments and agencies

C-NLOPB

10 Mar, 2016

Electronic transmission of Revised EA Update for 2016 to Responsible Authorities

C-NLOPB

24 Feb, 2016

2016 Environmental Assessment Update

HMDC

24 Feb, 2016

Submission of 2016 Environmental Assessment Update

HMDC

13 Aug, 2015

Electronic transmission of Revised EA Update for 2015 to NGO Fisheries

C-NLOPB

13 Aug, 2015

Electronic transmission of Revised EA Update for 2015 to government departments and agencies

C-NLOPB

13 Aug, 2015

Electronic transmission of Revised EA Update for 2015 to Responsible Authorities

C-NLOPB

12 Aug, 2015

Revised 2015 Environmental Assessment Update

HMDC

12 Aug, 2015

Submission of Revised 2015 Environmental Assessment Update

HMDC

21 May, 2015

Electronic transmission of EA Update for 2015 to NGO Fisheries

C-NLOPB

21 May, 2015

Electronic transmission of EA Update for 2015 to government departments and agencies

C-NLOPB

21 May, 2015

Electronic transmission of EA Update for 2015 to Responsible Authorities

C-NLOPB

1 May, 2015

Submission of 2015 Environmental Assessment Update

HMDC

16 Apr, 2015

2015 Environmental Assessment Update

HMDC

20 May, 2014

Revised 2014 Environmental Assessment Update

HMDC

5 May, 2014

Comments on 2014 Environmental Assessment Update

EC

5 May, 2014

Comments on 2014 Environmental Assessment Update

DFO

16 Apr, 2014

Request for comments from One Ocean and FFAW on 2014 Environmental Assessment Update

C-NLOPB

16 Apr, 2014

Request for comments from Government Departments and Agencies on 2014 Environmental Assessment Update

C-NLOPB

9 Apr, 2014

Submission of 2014 Environmental Assessment Update

HMDC

8 Apr, 2014

2014 Environmental Assessment Update

Stantec

31 Jul, 2013

2013 Environmental Assessment Update (Revised)

Stantec

31 Jul, 2013

Submission of 2013 Environmental Assessment Update (Revised)

Stantec

24 Jun, 2013

2013 Environmental Assesment Update (Revised)

Stantec

30 May, 2013

Electronic transmittal of 2013 Environmental Assessment Update to One Ocean and FFAW

C-NLOPB

30 May, 2013

Electronic transmittal of 2013 Environmental Assessment Update to Government Departments and Agencies

C-NLOPB

30 May, 2013

Electronic transmittal of 2013 Environmental Assessment Update to Responsible Authorities

C-NLOPB

29 May, 2013

2013 Environmental Assessment Update

Stantec

29 May, 2013

Submission of 2013 Environmental Assessment Update

Stantec

31 May, 2012

2012 Environmental Assessment Update (Revised)

Stantec

8 May, 2012

2012 Environmental Assessment Update

Stantec

21 Jun, 2011

2011 Environmental Assessment Update

Stantec

19 May, 2010

2010 Environmental Assessment Update

Stantec

21 Sep, 2009

EA Determination

C-NLOPB

15 Sep, 2009

Screening Report

C-NLOPB, DFO, EC

14 Sep, 2009

Consolidated HMDC Response to EA Review Comments

HMDC

14 Sep, 2009

HMDC Response to Request for Additional Information

HMDC

11 Sep, 2009

Request for Additional Information

C-NLOPB

31 Aug, 2009

Comment on Final EA Report

DFO

24 Jul, 2009

Consolidated HMDC Response to EA Review Comments

HMDC

24 Jul, 2009

Final EA Report

JW Ltd.

27 Jul, 2009

Comment on HMDC Response to Request for Additional Information

DFO

24 Jul, 2009

Transmittal of HMDC Response to Request for Additional Information

C-NLOPB

24 Jul, 2009

HMDC Response to Request for Additional Information

HMDC

23 Jul, 2009

Request for Additional Information

C-NLOPB

23 Jul, 2009

Comments on HMDC Response to Request for Additional Information

DFO

8 Jul, 2009

Transmittal of HMDC Response to Request for Additional Information

C-NLOPB

17 Jun, 2009

HMDC Response to Request for Additional Information

HMDC

15 Jun, 2009

EA Review Comments

C-NLOPB

15 Jun, 2009

Request for Additional Information

C-NLOPB

11 Jun, 2009

Response to HMDC Response to EA Review Comments

NRCanada

22 May, 2009

Comments on HMDC Response to EA Review Comments

EC

19 May, 2009

Comments on HMDC Response to EA Review Comments

DFO

28 Apr, 2009

Transmittal of HMDC Response to EA Review Comments

C-NLOPB

27 Apr, 2009

HMDC Response to EA Review Comments

HMDC

4 Mar, 2009

Electronic Transmittal of NR Canada EA Review Comments

C-NLOPB

3 Mar, 2009

EA Review Comments

NRCanada

2 Mar, 2009

Consolidated EA Review Comments

C-NLOPB

2 Mar, 2009

Request for Additional Information

C-NLOPB

22 Feb, 2009

EA Review Comments

DFO

13 Feb, 2009

EA Review Comment

EC

6 Feb, 2009

Response to Request for Review Comments

NDOEC

18 Dec, 2008

Transmittal of EA Report

C-NLOPB

17 Dec, 2008

Submission of EA Report

HMDC

16 Dec, 2008

EA Report

HMDC

7 Oct, 2008

Scoping Document

C-NLOPB

7 Oct, 2008

Notice of Determination & Provision of Scoping Document

C-NLOPB

29 Sep, 2008

FCR Determination

EC

29 Sep, 2008

FCR Determination

Transport Canada

25 Sep, 2008

FCR Determination

DFO

3 Sep, 2008

FCR Determination

NRCanada

28 Aug, 2008

Environmental Assessment Notification

C-NLOPB

28 Aug, 2008

Draft Scoping Document

C-NLOPB

28 Aug, 2008

FCR Notification

C-NLOPB

28 Aug, 2008

Submission of Project Description

HMDC

28 Aug, 2008

Project Description

HMDC

Scroll to view more

Operator Project CEAR # Status

BP Canada Energy Group ULC

BP Canada Energy Group ULC – Ephesus Prospect Controlled Source Electromagnetic (CSEM) Survey 2020-2024

Completed

BHP Canada

BHP Canada EXPL Drilling Project EL 1157 and 1158 Seabed Survey 2020-2025

Completed

Equinor Canada Ltd.

Equinor Canada Ltd. Central Ridge Exploration Drilling Project 2020-2029

80175

Completed

BP Canada Energy Group ULC

BP Canada Energy Group ULC – Ephesus Prospect ROV Survey 2019-2024

2022 EA Update Received

Equinor Canada Ltd.

Equinor Bay du Nord Development Project

80154

Completed

BP Canada Energy Group

BP Canada Energy Group ULC Newfoundland Orphan Basin Exploration Drilling Program, 2017-2026

80147

Completed

ExxonMobil Canada Ltd.

ExxonMobil Canada Limited Eastern Newfoundland Offshore Exploration Drilling Project 2018-2030

80132

2022 EA Update Received

Husky Oil Operations Limited and ExxonMobil Canada Limited

Jeanne D’Arc Exploration Drilling Project 2019-2027

80130

Completed

Equinor Canada Ltd. (formerly known as Statoil Canada Ltd.)

Equinor Canada Ltd. (Statoil Canada Ltd.) Flemish Pass Exploration Drilling Project 2018-2028

80129

Completed

Fugro GeoSurveys

Fugro GeoSurveys Offshore Seafloor and Seep Sampling Program, 2017-2027

Completed

Seitel’s

Seitel’s East Coast Offshore 2D 3D 4D Seismic Program 2016-2025

Completed

CGG

CGG Services (Canada) Inc. Newfoundland Offshore 2D 3D 4D Seismic Program 2016-2025

Completed

ExxonMobil

ExxonMobil Canada Eastern NL Geophysical Program 2015-2024

2022 EA Update Received

WesternGeco

WesternGeco Canada Eastern Newfoundland Offshore Seismic Program, 2015 to 2024

Undergoing Amendment

WesternGeco

WesternGeco Canada Southeastern Newfoundland Offshore Seismic Program, 2015 to 2024

Undergoing Amendment

Suncor Energy Inc

Suncor Energy’s Eastern Newfoundland Offshore Area 2D/3D/4D Seismic Program, 2014-2024

Completed

MG3

MG3 (Survey) UK Limited Offshore Labrador Geochemical and Seabed Sampling Program 2015-2024

Completed

Hibernia Management and Development Company Ltd.

Hibernia Management and Development Company Ltd. 2D/3D/4D Seismic Projects for the Hibernia Oil and Gas Production Field, 2013 to Remaining Life of Field

Completed

Husky Oil Operations Limited

Husky Oil Operations Limited White Rose Extension Project

12-01-68249

Completed

ExxonMobil Canada Properties

ExxonMobil Canada Properties Hebron Development Project

09-03-46144

Completed

HMDC

Hibernia Drill Centres Construction and Operations Program

08-01-42279

Completed

Petro-Canada

Terra Nova VSP Program

06-01-18277

Completed

Husky Energy

Husky Energy Drill Centre Construction Installation and Operation Program

06-01-17410

Completed